Why is my Gantt chart empty even after adding a project and milestones?
To view data in the Gantt chart, you must add Tasks under the Project or Project Milestones. Each task should have both Start Date & Time and End Date & Time fields filled in. The Gantt chart displays timelines based on these task dates, if no tasks or date values are defined, the chart will appear blank.