Follow these steps to add a timelog to a project task:

  1. Click the Main Menu.
  2. Go to the Projects tab.
  3. Select the Project Tasks module.
  4. Open any PT record.
  5. Click the +New button in the Summary View.
  6. Click Add or Create button.
  7. Select Timelogs.
  8. Fill in all the necessary details.
  9. Click Save to create a timelog.
    • Click Save and Continue to enter other information.

The linked timelog record will be visible in the Timelogs widget in the Summary View of the PT record.
 