FAQs in this section
What is Task sequencing?
What is a Task?
What are the dependencies between a subtask and a previous task?
What is the impact of business hours on Task duration?
What is a parent Task?
How do I delete a task?
How do I set up reminders for my Tasks?
How do I mass edit tasks?
How do I track time spent on a Task?
How do I use a Timelog?
How do I create invoices for a billable task?
What are the dependencies between Parent Tasks and Subtasks?
Can I see a Due Date in a Parent Task record?
How do I create a Previous Task?
How do I create a Parent Task?
How do I create a Subtask?
How do I access Tasks?
How do I create a Task?
What is an example of Task Sequencing?
Table of Contents
Here is an example of Task Sequencing:
Consider you have a parent task with three subtasks.
You add a previous task to Subtask 1. Subtask 1 can be marked as Completed only after Previous Task is completed. In this case, the start time of Subtask 1 gets updated to 6:30 PM.
Subtask 2 and Subtask 3 run independently of Subtask 1 and Previous Task. However, Parent Task can be marked as completed only after all subtasks are completed. The start date and time of Parent task is set to 5:15 PM and its due date and time is set to 7:30 PM.
Consider you have a parent task with three subtasks.
You add a previous task to Subtask 1. Subtask 1 can be marked as Completed only after Previous Task is completed. In this case, the start time of Subtask 1 gets updated to 6:30 PM.
Subtask 2 and Subtask 3 run independently of Subtask 1 and Previous Task. However, Parent Task can be marked as completed only after all subtasks are completed. The start date and time of Parent task is set to 5:15 PM and its due date and time is set to 7:30 PM.
Was this FAQ helpful?
0
out of
0
found this helpful.
Comments 0
Be the first to comment