FAQs in this section
How do I create a Task?
What is Task sequencing?
How do I create a subtask?
What is a Task?
How do I create a previous task?
What are the dependencies between a subtask and a previous task?
What is the impact of business hours on Task duration?
How do I create a parent task?
What is a parent Task?
What are the dependencies between parent tasks and subtasks?
How do I access Tasks?
How do I delete a task?
How do I set up reminders for my Tasks?
How do I mass edit tasks?
How do I track time spent on a Task?
How do I use a Timelog?
Can I see a due date in a parent task record?
How do I create invoices for a billable task?
What is an example of Task Sequencing?
Table of Contents
Here is an example of Task Sequencing:
Consider you have a parent task with three subtasks.
You add a previous task to Subtask 1. Subtask 1 can be marked as ‘Completed’ only after Previous Task is completed. In this case, the start time of Subtask 1 gets updated to 6:30 PM.
Subtask 2 and Subtask 3 run independently of Subtask 1 and Previous Task. However, Parent Task can be marked as completed only after all subtasks are completed. The start date and time of Parent task is set to 5:15 PM and its due date and time is set to 7:30 PM.
Consider you have a parent task with three subtasks.
You add a previous task to Subtask 1. Subtask 1 can be marked as ‘Completed’ only after Previous Task is completed. In this case, the start time of Subtask 1 gets updated to 6:30 PM.
Subtask 2 and Subtask 3 run independently of Subtask 1 and Previous Task. However, Parent Task can be marked as completed only after all subtasks are completed. The start date and time of Parent task is set to 5:15 PM and its due date and time is set to 7:30 PM.