FAQs in this section
How do I create a Task?
What is Task sequencing?
How do I create a subtask?
What is a Task?
How do I create a previous task?
What is the impact of business hours on Task duration?
How do I create a parent task?
What is a parent Task?
What are the dependencies between parent tasks and subtasks?
What is an example of Task Sequencing?
How do I access Tasks?
How do I delete a task?
How do I set up reminders for my Tasks?
How do I mass edit tasks?
How do I track time spent on a Task?
How do I use a Timelog?
Can I see a due date in a parent task record?
How do I create invoices for a billable task?
What are the dependencies between a subtask and a previous task?
Table of Contents
- You cannot change a subtask if it has a previous task. You cannot change its status to ‘Completed’ or modify its start time.
- During the creation of a subtask, the start date and time of the subtask are set to the due date and time of its previous task.
- If an existing subtask with no start date and time are edited and linked to a previous task, then the start date and time are updated with the previous task's due date (if specified).
- If an existing subtask whose start date and time are specified is edited and linked to a previous task with no start date and time, then the start date and time of the subtask are not overwritten by the value specified in its previous task.
- You can mark a subtask as completed only after completing its previous task.